Short answer: there is no single timeline, because it depends on the size of the building, its condition, the scope of work and any heritage protection. As a broad guide, on a typical villa project, design and permit approval together usually take six to twelve months before building starts. Construction then depends on the scope: even a complete renovation of a 100 square metre apartment typically takes around eight to ten months, and a larger villa or a heritage restoration takes longer.

This guide explains the stages in order, the permits you are likely to need and how long the law gives the authorities to decide, and what tends to slow projects down. It is written for owners renovating from the US, the UK and further afield, and reflects how we plan timelines on our own projects.

The stages of a renovation in Italy, in order

  1. Checks before you buy. Legal status, planning and heritage restrictions, the structure and the ground. See what to check before buying a property to renovate in Italy.
  2. Measured survey. Every wall and level of the existing building is measured and drawn up, because nothing in an old house is square.
  3. Concept and design. Layout, structure, services and interiors, developed until the design is fixed.
  4. Permits and approvals. The building permit, plus any heritage, landscape or seismic approvals the property needs.
  5. Tender and contract. Builders price the same detailed scope, and the contract is agreed.
  6. Construction. The build itself, with regular site supervision.
  7. Completion and sign-off. Final inspections, certificates and the filing that confirms the house can be lived in.

Stages three and four are where most of the waiting happens. Getting the design right before anything is submitted is the single best way to keep the rest of the timeline under control.

Which permit do you need, and how long does it take?

Italy’s national building rules set out three main routes. Which one applies depends on what you are changing. Regions and Comuni add their own rules on top, so your technician will confirm which applies to your property.

CILA: lighter works

A CILA (comunicazione di inizio lavori asseverata) covers lighter works, such as internal changes that do not affect the structure or the facade. It is a certified notice rather than an application, and works can start on the day it is filed.

SCIA: works affecting the structure or facade

A SCIA (segnalazione certificata di inizio attività) covers works that affect structural parts or the facade, restoration work, and lighter renovations. Works can usually start straight away, and the Comune then has 30 days to check the filing and stop the works if something is wrong.

Permesso di costruire: major renovations

A full building permit (permesso di costruire) is needed for heavier renovations, including works that add volume. By law, the Comune has up to 60 days to review the application and a further 30 days to decide, so about 90 days in total. That clock can be paused once while the Comune asks for more documents, and the review period can be doubled for complex projects.

Heritage and landscape approvals

If the property is formally listed, the Soprintendenza, the state heritage authority, must approve the design. If the land is under landscape protection, you also need a landscape authorisation (autorizzazione paesaggistica), in which the Soprintendenza gives a binding opinion. Under the ordinary procedure, the Soprintendenza has 45 days to give that opinion once it receives the file. In Lazio, for example, adding up the steps set out for the region and the Soprintendenza gives around three and a half months from a complete application, before any requests for more documents.

Structural work may also need a seismic filing or authorisation with the regional structural office, depending on the seismic zone. We explain how these rules work in practice on our historic villa restoration page.

Why the legal deadlines are not the real timeline

The statutory timescales are a useful guide, but they are not a promise. In practice:

  • The clock starts only when the application is complete. Requests for more documents pause or restart it.
  • Approvals often run in sequence. A heritage or landscape approval may be needed before the building permit can be issued.
  • The design has to be finished first. Time spent resolving the design is time before anything can be submitted.
  • August is quiet. Many offices and builders slow down or close around the mid-August holiday.

What slows a renovation down on site

  • Decisions made late. Settling choices such as the kitchen layout before work starts keeps the site moving. Changing your mind once walls are open costs time as well as money.
  • What you find in the walls and the ground. Old buildings hide surprises. Checking the structure and the ground before you buy reduces them.
  • Historic research. When a building must be restored to its original form and no archive photographs exist, a historical technician has to establish what it looked like first.
  • Specialist trades. Craftsmen for lime plaster, terracotta, stonework and historic joinery are in demand, so they need booking early.

How to keep your timeline on track

  • Do your checks before you buy, so there are fewer surprises.
  • Fix the design, including interiors, before you go to tender.
  • Have builders price the same detailed scope, so you are comparing like with like.
  • Agree a written programme before work starts, and track it every week.
  • Have one team accountable for design, permits and the site, especially if you are managing it from abroad.

This is how we run our own projects. You can see each stage on our process page, and what it all costs in our villa renovation cost guide.

Frequently asked questions

How long does it take to renovate a house in Italy?

It depends on size, condition, scope and any heritage protection. On a typical villa, allow six to twelve months for design and permits before work starts. Construction then varies with the scope: a complete renovation of a 100 square metre apartment typically takes around eight to ten months, and larger or listed properties take longer.

How long does a building permit take in Italy?

For a full building permit (permesso di costruire), the law gives the Comune about 90 days from a complete application, though this can be paused for more documents or extended for complex projects. Lighter works under a CILA or SCIA can usually start as soon as they are filed. Heritage and landscape approvals add further time.

Can I start work while waiting for permits?

Under a CILA or an ordinary SCIA, works can usually start once the filing is made. Works that need a full building permit, or heritage or landscape approval, cannot start until those are granted.

Do heritage-listed properties take longer to renovate?

Usually, yes. The Soprintendenza must approve the design, restoration work is slower and more specialised, and archive research may be needed before work can start.